News

07.02.2013

Construction activity in Montenegro The fourth quarter 2012


The value of finalised construction works in the fourth quarter 2012 is lower for 28.2% compared with the same quarter of previous year, while it is 7.5% lower compared with the third quarter of current year.

Effective hours worked on construction works in the fourth quarter 2012 are lower for 10.2% compared with the same quarter of previous year, while it is 0.2% lower compared with the third quarter of current year.

The value of new orders on buildings in the fourth quarter 2012 is higher for 203.8% compared with the same quarter of previous year, while it is 419.3% higher compared with the third quarter of current year.

The value of new orders on other buildings in the fourth quarter of 2012 is lower for 56.8% compared with the same quarter of previous year, while it is 100.4% higher compared with the third quarter of current year.

Release


Archive
Copyrights © 2025 All Rights Reserved by MONSTAT.